Working Thread - Mapping Critical Paths
This is a timeline which should be completed by KORG members, acts as a guide for Realizers for recommended or necessary deadlines. More specific Timeline: https://docs.google.com/spreadsheets/d/1gh0dia3BcNeqCpWFVw7J4va6ToWxiPADVuXElTp-qXk/edit#gid=0 Date |
Event |
---|---|
25.1.21 |
Confirmation of Event Date |
10.2.21 |
#1 Newsletter(?) date + realizer meeting invitation |
17.02.21 |
❤️Realizer Recruitment Evening |
03.03.21 |
#2 Newsletter |
Covid-19 Hygiene Concept Draft |
|
25.03.21 |
Opening of Kieze Registration |
25.02.21 |
Opening of the site planning map |
If necessary - 30.3.21 |
❤️ Realizer Recruitment Evening |
1.4.21 |
|
15.4.21 |
Kieze Leads Meeting |
1.5.21 |
#4 Newsletter |
?? June/July |
Tofu on Fire |
1.6.21 |
#5 Newsletter ! Hygiene Concept |
?? Confirm with ticketing |
Ticket sale & Dreams Voting starts |
Right upon tickets sale |
Volunteers Signup starts |
1.7.21 |
#6 Newsletter |
Precompression |
|
Dreams submission Period ends |
|
3 weeks before the event (for site planning) |
Kieze Registration Period ends |
#7 Newsletter |
|
2 weeks before event |
Dreams voting Period ends |
Communicate dreams budgets to dreamers |
|
#8 Newsletter |
|
General Assembly |
|
#9 Newsletter |
|
before the Build period starts |
Volunteer Sign up ends |
Early Crew Kiez Burn build starts |
|
3.8.21 |
#10 Newsletter |
5.8.21 |
Build Starts |
11.8.21 - 15.08.21 |
Kiez Burn |
18.8.21 |
Strike/tear-down ends |
Cris Tue 19 Jan 2021 11:07AM
I know this year's gonna let us practice spontaneity a lot, and more so at this stage we're now, but mental note for the future: based on what was criticized about last years, Dreams voting period should end early enough so the dreamers can realize their projects. No clue how much that would be, but surely more than 2 weeks, I guess.
Veroca R. Sala Mon 18 Jan 2021 9:09PM
Cool Thanks, bee! I added volunteers sign up starts & ends + added one newsletter before the realizers recruitment and a second realizers meeting. We still have the original timeline you made. sorry, i made these changes myself without consulting =/
Just a small note about the privacy of this thread, can't this be in the Planning group? 🤓
Bee · Wed 10 Feb 2021 9:14PM
@Franzi would you please mind giving your opinion on the rough draft here I have estimated for timings/dates...? Would like to present this at the Realizer's meeting and I'm pretty sure you were the mastermind behind critical paths before.