Timeline 2020 - Mapping Critical Paths

F Franzi Public Seen by 84

Last year, a central timeline was super useful. As discussed during our last meeting please fill in the data for your relevant areas:

Date

Event

?

Opening of Kieze Registration

?

Opening of the site planning map

06.03.2020

First Newsletter

11.03.2020

Dreams Submission Start + second Dreams launch newsletter

18.03.2020

Newsletter

Kieze Leads Meeting

1.04.2020

Newsletter

?.

Tofu on Fire

?

Ticket sale & Dreams Voting starts

22.04.2020

Newsletter

Precompression

30th of april

Dreams submission Period ends

1 week before the event

Kieze Registration Period ends

5th of may

Dreams voting Period ends

6.05.2020

Newsletter

10th of may

Communicate dreams budgets to dreamers

20.05.2020

Newsletter

General Assembly

3.06.2020

Newsletter

(...)

to be discussed

10.06.2020

Newsletter

12.06.

Kiez Burn build starts on Friday evening

15.06.2020

Newsletter

12.06.20

Build Starts

Wednesday 17.06. - Sunday 21.06

Kiez Burn

25.06.20

Strike/tear-down ends


@Purzel please fill in the contract signing deadlines for your areas

@Saskia (The Fuzzy Facilitator) can you check dream deadlines

@Keegan can you check build and strike dates?

@Otto & @Keegan can you check ticket dates?

@Alina, also known as Milda! can you check for Newsletter dates?

@Hanna-Maija (Animal) can you check for Kieze registration?

@Veroca R. Sala Can you check for volunteer coordination?

@Jan Thomas can you fill in event permission and AMT stuff?

DU

[deactivated account] Thu 12 Mar 2020 5:42PM

this is great @Franzi - I was looking at a way to make the Newsletter part of the timeframe - and you've just done it! Thanks!

To all concerned!

In the Communicorns Group, you will find two post for two Newsletters that are coming up. You can place the content you need communicated in there.

See here for 18th of MARCH: https://talk.kiezburn.org/d/oXafpQ93/-radically-regular-radically-do-ocratic-newsletter-march-18th-edition

P

Purzel Thu 12 Mar 2020 9:13PM

Do you think deadlines are necessary for my areas? I'm trying to get the contracts signed asap (depending on your go in terms of covid 19)

K

Keegan Sat 14 Mar 2020 3:42AM

Added build/strike dates based on current dates. Haven't added tickets yet as there is a lot and some are still TBC

F

Franzi Thu 12 Mar 2020 9:34PM

Can you map in the latest date to sign the offers? @Purzel